| 13:30 | COFFEE | ||
|---|---|---|---|
| 14:00 | Introduction + DSRP proposal | Tony | .pdf, .xls |
| 14:30 | Tech setup | Keith | see DS3 presn |
| 15:00 | DS3 Progress review & Stage02 Goals | Keith | |
| 15:30 | DS4 Progress review & Stage02 Goals | Markus | |
| 16:00 | DS5 Progress review & Stage02 Goals | Sebastien | |
| 16:30 | DS6 Progress review & Stage02 Goals | Bob/Tony | |
| 17:00 | Science goals for Stage02 | Nic/Richard | |
| 17:20 | Cross-DS Issues | ALL | |
| 18:00 | CLOSE | ||
| 09:00 | COFFEE | ||
|---|---|---|---|
| Board report and issues | Andy | |
| CDS Report | Francoise | |
| ESO Report | Markus | |
| INAF Report | Fabio | |
| AG Report | Richard | |
| ESA Report | Christophe |
| Role | Name | Attending |
|---|---|---|
| Board rep | AndyLawrence | no.. sorry guys |
| AstroGrid rep | RichardMcMahon | yes, arr Trieste Airport at 14:10(Wed); dep Trieste Airport at14:35(Thur) |
| CDS rep | FrancoiseGenova | yes |
| ESO rep | PaoloPadovani | yes |
| INAF rep | FabioPasian | yes (host!) |
| Project Manager | TonyLinde (chair) | yes |
| Project Scientist | NicholasWalton | no, available via telecon |
| Technical Lead | KeithNoddle | yes |
| DS3 Lead | KeithNoddle | yes |
| DS4 Lead | MarkusDolensky | yes |
| DS5 Lead | SebastienDerriere | yes |
| DS6 Lead | BobMann | no |
| ESA rep | ChristopheArviset (observing) | no, available via telecon |
| Code | Action | Who | By when | Comments |
|---|---|---|---|---|
| Tap02-01 | Track and push IVOA specs | DS Leads | ongoing | |
| Tap02-02 | Try accessing ACR from IDL | AlasdairAllan | ask him | ... |
| Tap02-03 | Try accessing Aladin from IDL | ThomasBoch | ask him | ... |
| Tap02-04 | Arrange collab meeting on PLASTIC | BobMann | 07-Oct-2005 | to define use cases and work towards protocol and prototypes |
| Tap02-05 | Look into science workshop | VOTC science team & Board | ?? | ... |
| Tap02-06 | Produce Stage02 Plan | TonyLinde | 07-Oct-2005 | ... |
| Tap02-07 | Send TL/KN server spec | PW | 30-Sep-2005 | ... |
| Tap02-08 | Clarify EU spend requirements and inform partners | AndyLawrence | 07-Oct-2005 | ... |
| Tap02-09 | Write up the DSL role & Agree with DSLs & Board | TonyLinde | 07-Oct-2005 | ... |
| Tap02-10 | ... | ... | dd-mmm-yy | ... |