Stage 01 Plan

This plan is derived from all the DS plans:

Goals

The major goals of Stage 01 (within the ProjectContract) are:
  • establish the project working environment
  • get the DS groups set up and working together
  • scope the DS areas
  • undertake intial investigations sufficient to plan future activities

Major Deliverables

Given that Stage01 effectively runs only from March-June, few of the funded staff will be hired until near the end of the period, and the Stage includes preparation and running of the EuroVOWorkshop (27-June to 01-July), there are not many deliverables and most are due at the end of the Stage.

The core deliverables for each DS area from the ProjectContract that fall within this Stage are:

Deliv Code Deliverable Name Month Comments
DS1
DS1-01 Project website 6 done
DS2
DS2-01 Project Plan 1 see ProjectPlan page
DS2-03 Science (Functionality) Framework Document 6 deferred to month 10

and from the DS Plans:

Deliv Code Deliverable Name Month Comments
DS3
s01ds3-01 Project working environment 6 Includes CVS, Maven, plans for testing sub-VO
s01ds3-02 Implementation of SIAP, SSAP, ConeSearch, OpenSkyQuery 6  
s01ds3-03 Security Study report 6  
s01ds3-04 Client-side UI Infrastructure Study report 6  
s01ds3-05 Outline project plan 6 draft plan for rest of project
DS4
s01ds4-01 Requirements specification of Cross Matching tool 6  
s01ds4-02 Java WebStart technology Evaluation report 6  
s01ds4-03 'Simple Footprint Preview' tool Specification and Prototype 6  
s01ds4-04 Prototype service demonstrating WCS-augmented graphics files in SIA 6  
s01ds4-05 Outline project plan 6 draft plan for rest of project
DS5
s01ds5-01 Existing tools and capabilities Evaluation report 6  
s01ds5-02 Agent infrastructure Requirements report 6  
s01ds5-03 Report on use of SAADA for extracting metadata 6  
s01ds5-04 Preliminary Ontology of object types 6  
s01ds5-05 Outline project plan 6 draft plan for rest of project
DS6
s01ds6-01 Data Exploration Scenarios 6  
s01ds6-02 List of 3rd Party tools for assessment 6  
s01ds6-03 Planning report for VisIVO & Astroneural 6  
s01ds6-04 Prototype of CEA-accessed grid-based codes 6  
s01ds6-05 Prototype of data manipulation tool for HDF5 cataqlogues 6  
s01ds6-06 Report on column-ordered data access 6 using STIL/TOPCAT
s01ds6-07 Report on use of k-d trees for indexing large catalogues 6  
s01ds6-08 Outline project plan 6 draft plan for rest of project

Milestones

The milestones for this Stage from the ProjectContract are:

Month Deliv Code Milestone Name Comments
+0   Kick-off Meeting done
+1   TAP meeting 1 done
+1 DS2-01 Project Plan  
+2   Stage 01 plan done (this is it)
+5   TAP meeting 2 will be in June
+6 DS1-01 Functioning project web site done
+6 DS2-03 Science Framework Document deferred to month 10
+6   Stage 02 plan  
end Stage01

No mid-term milestones are advanced for this Stage since it is the first and is only 4 months long. In effect there are two key milestones:

  1. 31st May: draft versions of deliverables need to be ready for the planning cycle for StageTwo
  2. 30th June: final versions of deliverables

Another key milestone is the EuroVOWorkshop: it is expected that VOTech personnel will contribute to the planning and execution of this event.

Edit | Attach | Printable | Raw View | Backlinks: Web, All Webs | History: r4 < r3 < r2 < r1 | More topic actions
 
This site is powered by the TWiki collaboration platformCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback