| Deliv Code | Deliverable Name | Original Deadline |
Revised Deadline |
Delivery Date |
Comments |
|---|---|---|---|---|---|
| Kick-off Meeting | 2004 Dec | n/a | 2004 Nov | done | |
| DS1 | |||||
| DS1-01 | Project website | 2005 Jun | 2005 Jun | 2005 Jan | done |
| DS2 | |||||
| DS2-01 | Project Plan | 2005 Jan | 2005 Jan | 2005 Mar | done: ProjectPlan |
| DS2-02 | Revised Project Plan | 2006 Jun | 2006 Sep | 2006 Dec | done: see Revisions on ProjectPlan |
| DS2-03 | Science (Functionality) Framework Document | 2005 Jun | 2006 Jun | 2007 Oct | done VotcSFD |
| DS2-04a | First Baseline software release | 2005 Dec | 2006 Mar | 2006 Mar | done: SoftwareDownload |
| DS2-04b | Second Baseline software release | 2006 Dec | 2007 Mar | 2007 Mar | done: SoftwareDownload |
| DS2-04c | Third Baseline software release | 2007 Dec | 2008 Mar | 2008 Apr | done: SoftwareDownload |
| DS2-04d | Fourth Baseline software release | 2008 Jun | 2008 Sep | done: SoftwareDownload | |
| DS2-05 | Euro-VO Reference Architecture | 2008 Dec | 2008 Dec | done | |
| DS3 | |||||
| DS3-01 | Infrastructure Study Report | 2006 Mar | 2006 Jun | 2007 Jan | done InfrastructureDesignStudyReport |
| DS3-02 | First Infrastructure Prototype release to DS2 | 2006 Dec | 2007 Mar | 2007 Mar | included in baseline |
| DS3-03 | Second Infrastructure Prototype release to DS2 | 2007 Dec | 2008 Mar | 2008 Apr | included in baseline |
| DS3-04 | Third Infrastructure Prototype release to DS2 | 2008 Jun | 2008 Sep | ||
| DS4 | |||||
| DS4-01 | User Tools Study Report | 2007 Mar | 2007 Jun | 2007 Jun | done: DS4StudyReport |
| DS4-02 | First User Tools Prototype release to DS2 | 2007 Jun | 2007 Sep | 2007 Oct | done: DS4ReleaseOne |
| DS4-03 | Second User Tools Prototype release to DS2 | 2007 Dec | 2008 Mar | 2008 Mar | done: DS4ReleaseTwo |
| DS4-04 | Third User Tools Prototype release to DS2 | 2008 Jun | 2008 Sep | ||
| DS5 | |||||
| DS5-01 | Resource Discovery Study Report | 2007 Sep | 2007 Dec | 2008 Sep | done: DS5StudyReport |
| DS5-02 | First Resource Discovery Prototype release to DS2 | 2007 Jun | 2007 Sep | 2007 Oct | done: ResourceDiscoveryPrototype1 |
| DS5-03 | Second Resource Discovery Prototype release to DS2 | 2007 Dec | 2008 Mar | 2008 Apr | included in baseline |
| DS5-04 | Third Resource Discovery Prototype release to DS2 | 2008 Jun | 2008 Sep | ||
| DS6 | |||||
| DS6-01 | Data Exploration Study Report | 2006 Sep | 2006 Dec | 2007 Feb | done: DS6StudyReport |
| DS6-02 | First Data Exploration Prototype release to DS2 | 2006 Dec | 2007 Mar | 2007 Mar | included in baseline |
| DS6-03 | Second Data Exploration Prototype release to DS2 | 2007 Dec | 2008 Mar | 2008 Apr | included in baseline |
| DS6-04 | Third Data Exploration Prototype release to DS2 | 2008 Jun | 2008 Sep | ||
| Deliverable Name | Link* |
|---|---|
| 1st Annual Report | http://wiki.eurovotech.org/twiki/pub/VOTech/ProjectContract/votech-1st-annual-report.pdf |
| 2nd Annual Report | http://wiki.eurovotech.org/twiki/pub/VOTech/ProjectContract/votech-2nd-annual-report-partA.doc |
| Mid Term Review | FormalReviewMaterials |
| 3rd Annual Report | http://wiki.eurovotech.org/twiki/pub/VOTech/ProjectContract/votech-3rd-annual-report-partA.pdf |
| 4th Annual Report | to come |
| Final Report | to come |
| Deliv Code | Milestone Name | Original Deadline |
Revised Deadline |
Delivery Date |
Comments |
|---|---|---|---|---|---|
| Kick-off Meeting | 2004 Dec | --- | 2004 Nov | ||
| DS2-01 | Project Plan | 2005 Jan | --- | 2005 Mar | ProjectPlan |
| Stage01 plan | 2005 Feb | 2005 Mar | 2005 Mar | see StageOnePlan (Note 01) | |
| TAP meeting 1 | 2005 Jan | 2005 Mar | 2005 Mar | Note 01 | |
| Stage02 plan | 2005 Jun | 2005 Mar | 2005 Mar | see StagePlans | |
| TAP meeting 2 | 2005 May | 2005 Sep | 2005 Sep | ||
| DS1-01 | Functioning Project web site | 2005 Jun | --- | 2005 Jan | |
| DS2-03 | Science Framework Document | 2005 Jun | 2006 Jun | 2007 Oct | see VotcSFD (Note 02) |
| Stage03 plan | 2005 Dec | 2006 Mar | 2006 Mar | ||
| TAP meeting 3 | 2005 Nov | 2006 Mar | 2006 Apr | ||
| Consortium + Board Meeting 1 | 2005 Nov | --- | 2005 Jun | Note 03 | |
| DS2-04a | Baseline software release-1 | 2005 Dec | 2006 Mar | 2006 Mar | see SoftwareDownload |
| Demonstration event | 2006 Jan | --- | 2006 Apr | Note 04 | |
| DS3-01 | Infrastructure Study Report | 2006 Mar | 2006 Jun | 2007 Jan | see InfrastructureDesignStudyReport (Note 05) |
| Stage04 plan | 2006 Jun | 2006 Sep | 2006 Oct | ||
| TAP meeting 4 | 2006 May | 2006 Sep | 2006 Dec | ||
| DS2-02 | Revised Project Plan | 2006 Jun | 2006 Sep | 2006 Dec | see VOTECH-PP-revisions-2006-dec.pdf |
| DS6-01 | Data Exploration Study Report | 2006 Sep | 2006 Dec | 2007 Jan | see DS6StudyReport (Note 05) |
| Stage05 plan : DSRP | 2006 Dec | 2007 Mar | 2007 Mar | ||
| Stage05 plan : TAP | 2006 Nov | 2007 Mar | 2007 Apr | combined with Board-4 | |
| Board Meeting 3 | ---- | ---- | 2006 Dec | Note 06 | |
| DS3-02 | DS3 Prototype releases to DS2 | 2006 Dec | 2007 Mar | 2007 Mar | |
| DS6-02 | DS3 Prototype releases to DS2 | 2006 Dec | 2007 Mar | 2007 Mar | |
| DS2-04b | Baseline software release 2 | 2006 Dec | 2007 Apr | 2007 Apr | |
| Demonstration event | 2007 Jan | 2007 Apr | 2007 Jun | VOSAC at ESTEC | |
| DS4-01 | Tools Study Report | 2007 Mar | 2007 Jun | 2007 Jun | DS4StudyReport |
| Board Meeting 4 | ---- | ---- | 2007 Apr | Note 06 | |
| Stage 06 plan : DSRP | 2007 May | 2007 Sep | 2007 Oct | ||
| Stage 06 plan : TAP | 2007 May | 2007 Sep | 2007 Nov | combined with Board-5 | |
| Board Meeting 5 | ---- | ---- | 2007 Nov | Note 06 | |
| DS4-02 | DS4 Prototype releases to DS2 | 2007 Jun | 2007 Sep | 2007 Oct | DS4ReleaseOne |
| DS5-02 | DS5 Prototype releases to DS2 | 2007 Jun | 2007 Sep | 2007 Oct | ResourceDiscoveryPrototype1 |
| DS5-01 | Resource Discovery Study Report | 2007 Sep | 2007 Dec | 2008 Oct | |
| Stage 07 plan : DSRP | ---- | 2008 Mar | 2008 Mar | ||
| Stage 07 plan : TAP | 2007 Nov | 2008 Mar | 2008 Apr | plan agreed by email | |
| DS4-03 | DS4 Prototype releases to DS2 | 2007 Dec | 2008 Mar | 2008 Mar | DS4ReleaseTwo |
| DS3-03 | DS3 Prototype releases to DS2 | 2007 Dec | 2008 Mar | 2008 Mar | SoftwareDownload |
| DS5-03 | DS5 Prototype releases to DS2 | 2007 Dec | 2008 Mar | 2008 Mar | SoftwareDownload |
| DS6-03 | DS6 Prototype releases to DS2 | 2007 Dec | 2008 Mar | 2008 Mar | SoftwareDownload |
| DS2-04c | Baseline software release 3 | 2007 Dec | 2008 Mar | 2008 Mar | SoftwareDownload |
| Demonstration event | 2008 Jan | 2008 Apr | 2008 Mar | VOSAC at Cambridge | |
| Stage 08 plan : DSRP | --- | 2008 Sep | 2008 Sep | ||
| Stage 08 plan : TAP | 2008 May | 2008 Sep | 2008 Dec | combined with Board-7 | |
| Board Meeting 6 | ---- | ---- | 2008 Oct | Note 06 | |
| Board Meeting 7 | ---- | ---- | 2008 Dec | Note 06 | |
| Demonstration event | ---- | 2008 Nov | 2008 Dec | VOSAC at Strasbourg | |
| DS2-05 | Euro-VO Reference Architecture | 2008 Dec | 2008 Dec | Note 07 | |
| DS3-04 | DS3 Prototype releases to DS2 | 2008 Jun | 2008 Sep | ||
| DS4-04 | DS4 Prototype releases to DS2 | 2008 Jun | 2008 Sep | ||
| DS5-04 | DS5 Prototype releases to DS2 | 2008 Jun | 2008 Sep | ||
| DS6-04 | DS6 Prototype releases to DS2 | 2008 Jun | 2008 Sep | ||
| DS2-04d | Baseline software release 4 | 2008 Jun | 2008 Sep |
| I | Attachment | Action | Size | Date | Who | Comment |
|---|---|---|---|---|---|---|
| |
VOTECH-reference-architecture-20090630.pdf | manage | 75.1 K | 2009-07-04 - 21:42 | AndyLawrence | VOTECH Reference Architecture |
| |
VOTECH-reference-architecture.pdf | manage | 75.1 K | 2009-07-04 - 21:48 | AndyLawrence | VOTECH Reference Architecture |
| |
votech-2nd-annual-report-partA.doc | manage | 336.0 K | 2007-09-18 - 21:34 | AndyLawrence | Second Annual Report |