Project Contract: Deliverables and Milestones

The complete project plan can be found in ProjectPlan. Here we provide the key Reports provided by the Project, tabulate the Deliverables and Milestones, and track their progress.

Project Reports

Project Deliverables

Deliv Code Deliverable Name Original
Deadline
Revised
Deadline
Delivery
Date
Comments
  Kick-off Meeting 2004 Dec n/a 2004 Nov done
DS1
DS1-01 Project website 2005 Jun 2005 Jun 2005 Jan done
DS2
DS2-01 Project Plan 2005 Jan 2005 Jan 2005 Mar done: ProjectPlan
DS2-02 Revised Project Plan 2006 Jun 2006 Sep 2006 Dec done: see Revisions on ProjectPlan
DS2-03 Science (Functionality) Framework Document 2005 Jun 2006 Jun 2007 Oct done VotcSFD
DS2-04a First Baseline software release 2005 Dec 2006 Mar 2006 Mar done: SoftwareDownload
DS2-04b Second Baseline software release 2006 Dec 2007 Mar 2007 Mar done: SoftwareDownload
DS2-04c Third Baseline software release 2007 Dec 2008 Mar 2008 Apr done: SoftwareDownload
DS2-04d Fourth Baseline software release 2008 Jun 2008 Sep   done: SoftwareDownload
DS2-05 Euro-VO Reference Architecture 2008 Dec 2008 Dec   done
DS3
DS3-01 Infrastructure Study Report 2006 Mar 2006 Jun 2007 Jan done InfrastructureDesignStudyReport
DS3-02 First Infrastructure Prototype release to DS2 2006 Dec 2007 Mar 2007 Mar included in baseline
DS3-03 Second Infrastructure Prototype release to DS2 2007 Dec 2008 Mar 2008 Apr included in baseline
DS3-04 Third Infrastructure Prototype release to DS2 2008 Jun 2008 Sep    
DS4
DS4-01 User Tools Study Report 2007 Mar 2007 Jun 2007 Jun done: DS4StudyReport
DS4-02 First User Tools Prototype release to DS2 2007 Jun 2007 Sep 2007 Oct done: DS4ReleaseOne
DS4-03 Second User Tools Prototype release to DS2 2007 Dec 2008 Mar 2008 Mar done: DS4ReleaseTwo
DS4-04 Third User Tools Prototype release to DS2 2008 Jun 2008 Sep    
DS5
DS5-01 Resource Discovery Study Report 2007 Sep 2007 Dec 2008 Sep done: DS5StudyReport
DS5-02 First Resource Discovery Prototype release to DS2 2007 Jun 2007 Sep 2007 Oct done: ResourceDiscoveryPrototype1
DS5-03 Second Resource Discovery Prototype release to DS2 2007 Dec 2008 Mar 2008 Apr included in baseline
DS5-04 Third Resource Discovery Prototype release to DS2 2008 Jun 2008 Sep    
DS6
DS6-01 Data Exploration Study Report 2006 Sep 2006 Dec 2007 Feb done: DS6StudyReport
DS6-02 First Data Exploration Prototype release to DS2 2006 Dec 2007 Mar 2007 Mar included in baseline
DS6-03 Second Data Exploration Prototype release to DS2 2007 Dec 2008 Mar 2008 Apr included in baseline
DS6-04 Third Data Exploration Prototype release to DS2 2008 Jun 2008 Sep    

Contractual Deliverables

Deliverable Name Link*
1st Annual Report http://wiki.eurovotech.org/twiki/pub/VOTech/ProjectContract/votech-1st-annual-report.pdf
2nd Annual Report http://wiki.eurovotech.org/twiki/pub/VOTech/ProjectContract/votech-2nd-annual-report-partA.doc
Mid Term Review FormalReviewMaterials
3rd Annual Report http://wiki.eurovotech.org/twiki/pub/VOTech/ProjectContract/votech-3rd-annual-report-partA.pdf
4th Annual Report to come
Final Report to come

Milestones Summary

(from VOTECH-PP-revisions-2006-dec.pdf)
Deliv Code Milestone Name Original
Deadline
Revised
Deadline
Delivery
Date
Comments
  Kick-off Meeting 2004 Dec --- 2004 Nov  
DS2-01 Project Plan 2005 Jan --- 2005 Mar ProjectPlan
  Stage01 plan 2005 Feb 2005 Mar 2005 Mar see StageOnePlan (Note 01)
  TAP meeting 1 2005 Jan 2005 Mar 2005 Mar Note 01
  Stage02 plan 2005 Jun 2005 Mar 2005 Mar see StagePlans
  TAP meeting 2 2005 May 2005 Sep 2005 Sep  
DS1-01 Functioning Project web site 2005 Jun --- 2005 Jan  
DS2-03 Science Framework Document 2005 Jun 2006 Jun 2007 Oct see VotcSFD (Note 02)
  Stage03 plan 2005 Dec 2006 Mar 2006 Mar  
  TAP meeting 3 2005 Nov 2006 Mar 2006 Apr  
  Consortium + Board Meeting 1 2005 Nov --- 2005 Jun Note 03
DS2-04a Baseline software release-1 2005 Dec 2006 Mar 2006 Mar see SoftwareDownload
  Demonstration event 2006 Jan --- 2006 Apr Note 04
DS3-01 Infrastructure Study Report 2006 Mar 2006 Jun 2007 Jan see InfrastructureDesignStudyReport (Note 05)
  Stage04 plan 2006 Jun 2006 Sep 2006 Oct  
  TAP meeting 4 2006 May 2006 Sep 2006 Dec  
DS2-02 Revised Project Plan 2006 Jun 2006 Sep 2006 Dec see VOTECH-PP-revisions-2006-dec.pdf
DS6-01 Data Exploration Study Report 2006 Sep 2006 Dec 2007 Jan see DS6StudyReport (Note 05)
  Stage05 plan : DSRP 2006 Dec 2007 Mar 2007 Mar  
  Stage05 plan : TAP 2006 Nov 2007 Mar 2007 Apr combined with Board-4
  Board Meeting 3 ---- ---- 2006 Dec Note 06
DS3-02 DS3 Prototype releases to DS2 2006 Dec 2007 Mar 2007 Mar  
DS6-02 DS3 Prototype releases to DS2 2006 Dec 2007 Mar 2007 Mar  
DS2-04b Baseline software release 2 2006 Dec 2007 Apr 2007 Apr  
  Demonstration event 2007 Jan 2007 Apr 2007 Jun VOSAC at ESTEC
DS4-01 Tools Study Report 2007 Mar 2007 Jun 2007 Jun DS4StudyReport
  Board Meeting 4 ---- ---- 2007 Apr Note 06
  Stage 06 plan : DSRP 2007 May 2007 Sep 2007 Oct  
  Stage 06 plan : TAP 2007 May 2007 Sep 2007 Nov combined with Board-5
  Board Meeting 5 ---- ---- 2007 Nov Note 06
DS4-02 DS4 Prototype releases to DS2 2007 Jun 2007 Sep 2007 Oct DS4ReleaseOne
DS5-02 DS5 Prototype releases to DS2 2007 Jun 2007 Sep 2007 Oct ResourceDiscoveryPrototype1
DS5-01 Resource Discovery Study Report 2007 Sep 2007 Dec 2008 Oct  
  Stage 07 plan : DSRP ---- 2008 Mar 2008 Mar  
  Stage 07 plan : TAP 2007 Nov 2008 Mar 2008 Apr plan agreed by email
DS4-03 DS4 Prototype releases to DS2 2007 Dec 2008 Mar 2008 Mar DS4ReleaseTwo
DS3-03 DS3 Prototype releases to DS2 2007 Dec 2008 Mar 2008 Mar SoftwareDownload
DS5-03 DS5 Prototype releases to DS2 2007 Dec 2008 Mar 2008 Mar SoftwareDownload
DS6-03 DS6 Prototype releases to DS2 2007 Dec 2008 Mar 2008 Mar SoftwareDownload
DS2-04c Baseline software release 3 2007 Dec 2008 Mar 2008 Mar SoftwareDownload
  Demonstration event 2008 Jan 2008 Apr 2008 Mar VOSAC at Cambridge
  Stage 08 plan : DSRP --- 2008 Sep 2008 Sep  
  Stage 08 plan : TAP 2008 May 2008 Sep 2008 Dec combined with Board-7
  Board Meeting 6 ---- ---- 2008 Oct Note 06
  Board Meeting 7 ---- ---- 2008 Dec Note 06
  Demonstration event ---- 2008 Nov 2008 Dec VOSAC at Strasbourg
DS2-05 Euro-VO Reference Architecture 2008 Dec 2008 Dec   Note 07
DS3-04 DS3 Prototype releases to DS2 2008 Jun 2008 Sep    
DS4-04 DS4 Prototype releases to DS2 2008 Jun 2008 Sep    
DS5-04 DS5 Prototype releases to DS2 2008 Jun 2008 Sep    
DS6-04 DS6 Prototype releases to DS2 2008 Jun 2008 Sep    
DS2-04d Baseline software release 4 2008 Jun 2008 Sep    

Milestone notes

01: The project was started with a 3 month preliminary investigation and exploration phase, while recruitment was still taking place. The formal six month work cycles ("Stages") were therefore started April 1st 2005. Many key milestones were planned to coincide with the work planning cycle, and so were slipped by three months. This and a few other milestone changes were agreed by the Board and consolidated in a revised project plan issued in December 2006. "Revised deadline" in tables above refer to these formally agreed changes as of Dec 2006. Note that the first cycle plan, and the TAP meeting approving it, were completed before the start of the first formal cycle.

02: The VOTECH Science Framework Document (SFD) was delayed while the science advisory structure for Euro-VO overall was set up. Version 1.0 of the SFD was released Oct 2007.

03: It was originally envisaged that full consortium meetings would be held once a year, with a Board meeting during or immediately after the full consortium meeting. In fact full open consortium meetings are held twice a year as part of the work planning cycle (the DSRP meetings), and formal Board meetings are held as required to take policy decisions. As of December 2006, we have decided to merge TAP and Board meetings, and aim to hold these a few weeks after each DSRP meeting.

04: "Demonstration events" have been held within a Euro-VO context, by demonstrations of progress to the Euro-VO Science Advisory Committee (VO-SAC). The first of these was held in Garching, April 27-28 2006, the second in Frascati, November 22nd, and have continued since.

05: Note that the DS3 (Infrastructure) and DS6 (Data Exploration) Study Reports are labelled "preliminary". This is only because the study groups concerned wished to reserve the ability to issue an updated report later in the project; these "preliminary" reports are in fact full reports and constitute the formal VOTECH deliverables.

06: This was not a full consortium meeting, as these are now held twice yearly (the DSRP meetings).

07 : The Reference Architecture is now scheduled for completion during the extended close-out phase, Jan-May 2009.

Note on Funding time-table

The modalities of further payments are closely linked to the reporting cycle:

Jan 2006: we provide a report on P1 (2005). On approval of the report, we get pre-financing of 80% of P2 (2006) and 40% of P3, paid within 45 days of approval of the report, that is, about March 2006. Payment will be adjusted in light of over- or under-spend of pre-financing.

Jan 2007: we provide report on P1 + P2 and get the finances audited. On approval of the reports, we get payment to settle the approved payments in P1 and P2 plus pre-financing 80% of P3 (2007) and 40% of P4, paid within 45 days of approval, say March 2007.

Jan 2008: we provide a report on P3 (as for P1, i.e. no audit) and, following approval, get the last bit of pre-payment (80% of P4) in about March 2008.

Jan 2009: we provide final report, including audited reports on P3 + P4, and get final payment to settle approved costs.

-- PeredurWilliams - 03 Aug 2005

Topic attachments
I Attachment Action Size Date Who Comment
pdfpdf VOTECH-reference-architecture-20090630.pdf manage 75.1 K 2009-07-04 - 21:42 AndyLawrence VOTECH Reference Architecture
pdfpdf VOTECH-reference-architecture.pdf manage 75.1 K 2009-07-04 - 21:48 AndyLawrence VOTECH Reference Architecture
docdoc votech-2nd-annual-report-partA.doc manage 336.0 K 2007-09-18 - 21:34 AndyLawrence Second Annual Report
Topic revision: r27 - 2009-07-04 - 21:51:19 - AndyLawrence
 
This site is powered by the TWiki collaboration platformCopyright © by the contributing authors. All material on this collaboration platform is the property of the contributing authors.
Ideas, requests, problems regarding TWiki? Send feedback