DS3 Stage01 Plans
Plans and actions for Stage01, due for delivery 30th June 2005
Activities
CVS Repository
Create a CVS repository for VOTech sources, intially using AstroGrid resources. Provide secure Shell (SSH) access to the repository for authorised users. Include repository in scheduled backups. Migrate to VOTech systems when available.
Maven build environment
Create a build environment based upon the AstroGrid environment. Provide usage help and produce outline process if required. Discuss with partners.
Publishing site
Create web site for publishing VOTech software. Initially use AstroGrid hosts, but migrate to VOTech systems when available.
1::Many FileManager::FileStore support
Provide true distributed file storage based upon AstroGrid MySpace V2 component.
CEA proxy for SIAP, SSAP, ConSearch, OpenSkyQuery
Investigate and implement wider access to on-line resources from the AstroGrid CEA Proxy service.
Native JES support for SIAP, SSAP, ConSearch, OpenSkyQuery
Investigate and plan migration of above support directly into AstroGrid JES component
Prototype client-side GUI workflow builder application
In conjunction with the Workflow Use Case activity below, investigate and develop a prototype client-side GUI workflow builder. Include evaluation of exisiting tools (Taverna, Triana etc) as well as integration with AstroGrid Dashboard and JES components
Security report
Based upon current requirements and IVOA agreements (or at least, converging discussions), publish a report providing security implementation guidelines for VOTech developmenst in the short and medium terms.
Client-side User Interface report
Based upon experience of using the AstroGrid-2 Dashboard with various client-side applications, publish a report recommending further research and implementation guidelines.
DSA to provide SIAP, SSAP, ConSearch, OpenSkyQuery interfaces report
Investigate and publish a report recommending the viability and best approach to providing the above interfaces from the AstroGrid DSA component
Develop Use Cases for generic workflow requirements
By examining existing and expected usage models, develop and publish Use Cases defining the role of workflow in the VO environment
Develop profiles (and examine existing) for web services, report
Publish web service profiles for discussion at the IVOA Interop meeting in Kyoto
Vizier-ADQL
ADQL is easy to implement over relational databases but "VizieR" is not a "relational database"
Investigate how to implement ADQL in this context (wrapping, etc.)
Plan
| Environment |
| Deliverable | Who | Delivery Date | Status |
| CVS Repository | Catherine Qin | 30 June | Awaiting VOTech hardware |
| Maven build environment | Catherine Qin | 30 June | Awaiting h/w and reqs feedback |
| Publishing site | Catherine Qin | 30 June | In progress |
| Infrastructure |
| Deliverable | Who | Delivery Date | Status |
| 1::Many FileManager::FileStore support | Noel Winstanley | 29-April | Done |
| CEA proxy for SIAP, SSAP, ConSearch, OpenSkyQuery | Paul Harrison | 27 May | Update reqd |
| Native JES support for SIAP, SSAP, ConSearch, OpenSkyQuery | Paul Harrison | 30 June | Update reqd |
| Prototype client-side GUI workflow builder application | Andre Schaaff (and trainee : Cyril Pestel) | 30 June | Done - Available at CDS devcorner |
| Studies |
| Deliverable | Who | Delivery Date | Status |
| Security report | Guy Rixon | 30 June | Update reqd |
| Client-side User Interface report | Noel Winstanley | 30 June | Done (pdf attached) |
| DSA to provide SIAP, SSAP, ConSearch, OpenSkyQuery interfaces; report | Dave Morris | 30 June | Update reqd |
| Develop Use Cases for generic workflow requirements | Andre Schaaff (and CDS working group) | 27 May | Done |
| Develop profiles (and examine existing) for web services, report | Andre Schaaff | 12 May | Done - IVOA Document |
| Investigate requirements for adding support for ADQL queries to Vizier, report | Andre Schaaff | 30 September | Done - Madrid Interop |
Actions
| Who | What | When | Status |
| All | Discuss, amend and finalise deliverables | 9 March | Done |
| All | Approve Activities and Plan above | 14 March | Done |
| KN | Develop project plan, assign tasks | 30 March | Done |
| All | Status update required | 10 June | On-going |
Note: The assignments are against the directly responsible individual; other DS3 resources may be required for implementation purposes
--
KeithNoddle - 03 Mar 2005